Denver airport boosts efforts to help travelers navigate construction as council considers new contracts

As Denver Worldwide Airport works to restart its troubled terminal renovation venture, it’s putting in clearer signage to assist confused vacationers navigate the maze of building partitions and relocating a drive-through baggage drop station in order that extra passengers can simplify their journey.

Offered by Denver Worldwide Airport

Examples of directional flooring decals put in lately within the terminal at Denver Worldwide Airport.

“What I hear from my constituents most is that their experience at the airport stinks right now,” Denver Metropolis Councilwoman Amanda Sawyer instructed DIA officers throughout a latest committee listening to.

Because the airport terminated its public-private partnership take care of Nice Corridor Companions in August, it’s been responding to such complaints by changing current indicators and hiring extra workers and “ambassadors” to assist direct folks.

Probably the most seen latest change is the position of flooring decals guiding vacationers to particular airline check-in counters, safety screening and different frequent locations.

And beginning Nov. 25, DIA’s distant drive-through bag drop will transfer from the Pikes Peak and Elbert satellite tv for pc parking tons to a extra handy location off the 75th Avenue exit of Peña Boulevard, the identical exit because the satellite tv for pc tons and rental automotive returns. That may permit extra folks to examine baggage off-site and get boarding passes printed earlier than they get dropped off on the terminal or park in any lot or storage.

The free possibility, accessible as much as 90 minutes earlier than home flights on Southwest, United, Delta, Spirit and American airways, ought to save a visit to the airline check-in counters, permitting passengers to move straight to safety. An identical bag examine already is obtainable on the airport’s transit station.

The Denver Metropolis Council is ready Monday night time to think about $136 million in contracts for the rebooted terminal venture, which DIA says will resume building early subsequent yr. The work is being organized within the type of contract extensions with corporations which have labored on different DIA initiatives: $32 million for brand new lead designer Stantec, $49 million for program supervisor Jacobs Engineering, $15 million for marketing consultant LS Gallegos, $20 million for transition contractor Sky Blue Builders, and $20 million for Gilmore Development, which is constructing a brand new safety screening management facility.

Nonetheless to come back in January is DIA’s contract with Hensel Phelps, the popular building contractor chosen to complete the primary part of the venture.

DIA officers plan to pin down a timeline and last funds by then, however renovation work isn’t anticipated to wrap up till 2024.

For now, officers say they’re aiming to maintain the venture below $770 million, together with the unique $650 million venture funds (as a part of Nice Corridor Companions’ bigger $1.eight billion association) and a $120 million contingency fund. Individually, DIA and Nice Corridor are nonetheless haggling over contract breakage charges which might be anticipated to value DIA between $170 million and $210 million.